Complete revamping of the hydroelectric power plant at the Mwadingusha station: implementation and commissioning of the 4 Andritz turbines DCS of 12,8 MW




Modernization of the DCS of the hydroelectric plant of the Vatnsfell site.


Complete DCS upgrade of the Krafla geothermal power plant (Island).




Upgrade of the remote control of the Nesjavellir geothermal power plant.


Revamping of the hydroelectric power plant on the Mavuzi site: implementation and commissioning of the 2 Charmilles turbines DCS of 5,5MW and 3 Neyrpic turbines DCS of 17MW




Revamping of the hydroelectric power plan on the Chicamba site: implementation and commissioning of the 2 Voith turbines DCS of 25MW


RTU TRACE143 upgrade for all Belgium electrical distribution substations. Setting and commissioning of IEC-870-5-104 communication protocol as a revamping of regional and national electrical distribution substations.



Implementation and commissioning of the DCS for the gas turbine DCS of Boutlelis (2 x 200MW)

Installation and commissioning of DCS of a thermal power station of +- 115MW in interface with the existing system and the Turbine Controller.



Revamping of a site equipped with 4 gas turbine of 3 x 30MW + 115MW

Installation and commissioning of 52 wind turbins of +- 2,5 MW, in partnership with GE wind.


430MW combined cycle control simulator

Addition of: a control PLC of pellet mills and links with existing Siemens I/O, a security BMS PLC, a remote I/O DCS for truck unloading



DCS of a 115MW gas turbine

Modification and modernisation of the DCS for the power plant with combined cycle of 360MW of Saint Ghislain to allow its telecontrol from Amercoeur power plant (distance +- 45km).



DCS for combined cycle of 430MW

DCS for units 3,4,5 & 6 (coal, oil and gas) RUIEN Power Plant for a total of 860MW



DCS for smoke treatment for units 3,4 & 5 (coal, oil and gas)

DCS installation and commissioning for a hydroelectric power plan on the Euphrates river équipped with 6 Francis turbines ( Neyrpic / Escher-Wyss) with vertical axis of 112MW each



DCS revamping of 4 Francis turbines with vertical axis of 38,5MW and supply of the DCS lot of 2 new Francis turbines with vertical axis of 150MW


News

  • 26 July 2018
    Did you see us on our stand at the World Nuclear Exhibition in Paris from June 26 to 28, 2018 - http://www.world-nuclear-exhibition.com/fr/Accueil/
  • 13 July 2018
    « Action nettoyage – Wallonie plus propre » in collaboration with SUSA from Mons on July 13th, 2018
All news